November 3, 2021: Phase 1A Construction Continues

Taft Street Paving – Phase 1A – 3rd roadway concrete placement to approximately Station 4+41 is complete.  This section ties Kemp Blvd into the new roadway.  Work Continues on next section of Roadway.  Phase 1A Roadway should be 95% complete in the next 30 days

Offsite Drainage Channel bottom section 100% complete.  Work continues on channel walls.

Offsite Drainage Channel Pilot Channel 96% complete.  Work continues on Pilot Channel.

Utility Drainage Piping Complete in Phase IA.

Planning begins for Phase 1B.  Tentative demo date is 1st week of December 2021.

Taft Driveways – Please note that a blue line has been marked on each driveway along Taft.  This blue line is the extent of driveway replacement and is marked so you can easily see where it begins.  Your new concrete approach that connects to the new street will begin at this blue line   This blue line is not the edge of the roadway.

Taft Street Location – The new roadway is 37’ wide from back of curb to back of curb.  The orange paint mark in center of Taft Blvd. is the centerline of the new roadway.  The back of curb for new roadway is 18’-6” from the orange dot each way.