October 13, 2021: Phase 1A Construction Continues

Offsite Drainage Channel bottom section 75% complete.  Work continues on channel bottom and walls.

Offsite Drainage Chaneel Pilot Channel 85% complete.  Work continues on Pilot Channel.

Taft Street Paving – Phase 1A – first street concrete placement scheduled for 10/13/2021 was delayed due to rain.

Utility Drainage Piping Complete in Phase IA.

Taft Driveways – Please note that a blue line has been marked on each driveway along Taft.  This blue line is the extent of driveway replacement and is marked so you can easily see where it begins.  Your new concrete approach that connects to the new street will begin at this blue line   This blue line is not the edge of the roadway.

Taft Street Location – The new roadway is 37’ wide from back of curb to back of curb.  The orange paint mark in center of Taft Blvd. is the centerline of the new roadway.  The back of curb for new roadway is 18’-6” from the orange dot each way.