Phase 1A street and guardrail demolition is complete.

Excavation for off-site concrete channel continues from just west of 5914 Taft Blvd along an existing earthen drainage channel heading north from Taft behind houses at Canyon Creek Circle.

Taft Driveways – Please note that a blue line has been marked on each driveway along Taft.  This blue line is the extent of driveway replacement and is marked so you can easily see where it begins.  Your new concrete approach that connects to the new street will begin at this blue line   This blue line is not the edge of the roadway.

Taft Street Location – The new roadway is 37’ wide from back of curb to back of curb.  The orange paint mark in center of Taft Blvd. is the centerline of the new roadway.  The back of curb for new roadway is 18’-6” from the orange dot each way.